CRL MT EDEN STATION – NAL PLATFORM

DATE OF PROJECT 2025

LOCATION CRL MT EDEN STATION

HEAD CONTRACTOR LINK ALLIANCE

work completed

Sansom was engaged by Link Alliance to apply Sikaflex 11FC White sealant to the platform joints at CRL Mt Eden Station (NAL Platform).

With only a one-day window during station downtime, our team successfully completed 90% of the 170-meter joint application through precise planning, teamwork, and coordination. The remaining 10% will be completed during night works while train operations are offline, demonstrating our flexibility and commitment to delivering under time-critical conditions.